KJZZ is a service of Rio Salado College,
and Maricopa Community Colleges

Copyright © 2024 KJZZ/Rio Salado College/MCCCD
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Mesa Light Rail Extension Starts Running Ahead Of Schedule

Starting today, the Mesa light rail extension will start running — seven months ahead of schedule. Construction on that line began January 2012.

On the other side of town, crews continue to work on the northwest extension — the line covering a stretch of 19th avenue. That line is not expected to be completed until 2016 — on time, but not ahead of schedule.

Both lines are just over 3 miles long. Corinne Holliday with Valley Metro said the northwest extension posed some additional construction challenges.

"Very early on, the northwest Phoenix light rail extension there was a lot more electrical lines that needed to be relocated so that took a little bit of extra time than anticipated, " said Holliday.

Holliday said around 500 miles of underground utilities had to be moved to accommodate the line, which runs from Bethany Home Road to Dunlap Avenue.

Updated 8/21/2015 at 10:45 a.m.

Tags
KJZZ senior field correspondent Kathy Ritchie has 20 years of experience reporting and writing stories for national and local media outlets — nearly a decade of it has been spent in public media.