SRP is planning what it calls an “energy center” about an hour south of Phoenix that would use a mix of solar, battery power and natural gas.
The project is one example of how utilities are trying to address an unprecedented demand for power, driven largely by data centers and large users.
SRP says it expects the Marigold Energy Center near Stanfield to harness 600 megawatts of solar power through the day, which would also charge the lithium ion batteries batteries with a capacity of 400 megawatts and could provide power for eight hours.
The natural gas component would ramp up to 675 megawatts during peak hours — like in the late afternoon and evening.
As Arizona’s utilities say they need to double their grid output in the coming years, they are tapping any resource they can get, whether it's renewable or fossil fuel.
SRP’s director of resource planning Bill McClellan says this site is part of that “all of the above approach.”
“We have to be able to maintain reliability at the same time that we're moving towards, you know, more carbon-free energy," McClellan said.
The other reason behind the approach is that the site is near natural gas infrastructure already.
"We've got the land that's available for the solar portion of the project, there's existing infrastructure and a 500 kV transmission line that SRP is able to utilize to interconnect into. And then it's also near existing natural gas pipelines owned by both El Paso and Transwestern. So really an ideal location to be able to host a lot of different types of generating resources in this one area," McClellan said.
SRP still needs to secure some regulatory approvals for the energy center. The utility is hosting open houses next week seeking public input.
-
A new strategy authorized by the Central Arizona Project would give cities and private utilities access to the Arizona Water Banking Authority's stored groundwater.
-
Hydropower generation between April and August was about 28% lower than the last 10-year average.
-
Arizona utility regulators are scheduled to vote on Tucson Electric Power’s request to increase electricity rates next week, but solar advocates want them to push the hearing until newly-elected officials take office next year.
-
Industrial and commercial customers like data centers continue to be the fastest growing customers for APS.
-
Advanced chipmaker TSMC could end up using the same amount of energy at its north Phoenix campus as approximately 300,000 homes. That’s according to new documents filed with the state’s utility regulator.